KA Block Update: August 2017

Progress continues apace on the KA Block in the Elliot Park neighborhood of East Town Minneapolis. Following are highlights as reported by our team members:

KA Headquarters, reported by Project Manager Ryan Klick:

  • Work station furniture is currently being installed on level 2, and will continue onto level 3 next week.

    finish work on coffee gallery counter
    Coffee gallery finish work, KA office
  • Punch list is currently being conducted on level 3 and will continue onto level 4 next week.
  • Concrete floor polishing is currently being installed on level 1 and will be complete next week.
  • Flooring is currently being installed on level 5 and will move to level 1 next week.
  • Millwork for level one will start to be installed next week.
  • Graphic wallcovering is complete on level 2 and will move up to levels 3 and 4 next week.
  • All in all we are in great shape for our October move in!

H.Q. Apartments, reported by Project Manager Chris Dokken:

webcam KA Block July 25, 2017
Webcam on the KA Block, July 25, 2017
  • Exterior metal panel installation continues.  Expect to complete east face of building (Portland side) in August
  • Skip will be removed at the end of July
  • Utility installation at Portland to start early September
  • KA conducted first owner punch list on 7/18 on first floor.  Will continue to complete floors moving up through the building
  • First two models units to be ready early September
  • Interior metal stud framing completed for the project
  • Taping and sanding drywall on level 9
  • Finish installation continues on lower floors (Level 2 – Level 8 – painting, cabinet installation, flooring, tile, etc.
  • Scheduled to turn the building over late February for rentals starting March 1, 2018

Finnegans House, reported by Project Manager Ryan Klick

Steel erection is underway with topping-off planned for August.

The Elliot Park Hotel– reported by Senior Project Manager Chad Rempe

Rendering of the KA Block
Rendering of KA Block. The Elliott Hotel is in the foreground.

KA has received a Notice to Proceed for hotel construction June 30, 2017. Since then it’s been a full court press to get superstructure procurement underway, including but not limited to the following:

  • Prepare, submit, review, approve, fabricate and deliver formwork systems
  • Prepare, submit, review, approve, fabricate and deliver reinforcing steel
  • Prepare, submit, review, approve, fabricate and deliver post-tensioned reinforcement

Based on current procurement progress we anticipate to begin vertical construction no later than August 14, 2017.